Transformer Commissioning Procedure

5.0 COMMISSIONING

5.1 PURPOSE

5.1.1 After the satisfactory completion of installation, the following pre-commissioning checks, and tests on instruments must be performed before putting the transformer into service. Prior to commissioning work, for specific help and information on the accessories supplied, refer to the manufacturer’s instruction booklet/product catalog, etc., furnished with the handing-over documents

5.2 COMMISSIONING TESTS

5.2.1 Insulation Resistance (IR)

Rajasthan Powergen

Before starting this test all the power terminal bushings should be thoroughly cleaned with a dry clean piece of cloth.

Rajasthan Powergen

At all the tap positions, IR values of windings to earth & between windings shall be measured with designated insulation tester of suitable ratings and readings noted.

Between HV Winding and Earth (Megger) use 5000V or 2500V Insulation Tester
Between HV and LV Winding (Megger) use 5000V or 2500V Insulation Tester
Between LV Winding and Earth (Megger) use 1000V or 500V Insulation Tester

Rajasthan Powergen

IR values obtained should be similar to those indicated in the manufacturers’ test report, furnished with the handing –over documents. In humid weather, IR values obtained may be lower due to condensation on the terminal bushings

Rajasthan Powergen

If IR values are very low and unacceptable, then it may be necessary to filter the oil / dry-out the winding till the insulation reaches satisfactory values.

5.2.2 Break-Down Voltage (BDV) Test:

Rajasthan Powergen

Oil samples from tank bottom, tank top, radiator, etc. shall be carefully taken and tested for BDV value, as per clause 4.3 of this manual.

Rajasthan Powergen

BDV value of oil should be more than 50kV (rms) for 1 minute in the standard test cell

Rajasthan Powergen

If BDV value is very low and unacceptable (30kV(rms) or less for 1 minute, then it may be necessary to dry-out & clean the oil till the insulation reaches satisfactory values.

Note: For very low IR values and low BDV values, it is recommended to contact suppliers or manufacturer for suitable recovery procedure based on available facilities at site

5.2.3 Voltage Ratio Test

Rajasthan Powergen

Apply 3-Phase, 433V AC supply on the HV side and the Voltage Ratio at all tap positions can be derived using suitable precision voltmeter connected to the LV side. A ratio meter, if available can be used for a more accurate measurement

Rajasthan Powergen

The Ratio value obtained should be similar to those indicated in the manufacturers’ test report, furnished with the handing-over documents.

5.2.4 Winding Resistance Measurement Test

Rajasthan Powergen

Winding Resistance of every phase of each winding should be measured using a suitable DC Resistive Bridge or similar.

Rajasthan Powergen

Winding Resistance values obtained should be similar to those indicated in the manufacturers’ test report, furnished with handing-over documents

5.2.5 Marshalling Box Scheme Check

Rajasthan Powergen

All the auxiliary wiring from various accessories to marshaling box shall be checked with marshaling box scheme drawing furnished with the handing-over documents.

Rajasthan Powergen

During testing of accessories like Buchholz relay, etc., an operation of all the alarm/trip contacts shall be checked at marshaling box terminal blocks ensuring both operation and wiring are checked correctly

5.2.6 Buchholz Relay Test

Rajasthan Powergen

Relay operation for alarm and trip contact shall be checked by injecting air inside the relay through test petcock. Injected air collected inside the relay allows the alarm float/flap & trip float/flap to fall thereby operating their respective switch

5.2.7 Temperature Indicator Test

Rajasthan Powergen

Indicators operation for alarm and trip contact shall be checked by manual stimulation

5.2.8 Off-Circuit Tap Selector (OCTS)

Rajasthan Powergen

During shipment, the OCTS has not been separated from the transformer so it is not necessary to recheck the internal connections of tapping an internal mechanism

Rajasthan Powergen

Means of protecting the OCTS from unauthorized operation is provided by using a padlocking arrangement at the designated tap position

5.3 SENSIBLE ADDITIONAL CHECKS

5.3.1 BEFORE SWITCH ON ENSURE that

Rajasthan Powergen

All the Oil Shut-off Valves are OPEN and Draw-Off Valves are CLOSED

Rajasthan Powergen

All Thermometer Pockets are near filled (85%) with oil.

Rajasthan Powergen

Oil is at the correct level in the Bushings, Conservator, etc

Rajasthan Powergen

Desiccant color in breather is blue for silica-gel or yellow/orange for envirogel

Rajasthan Powergen

Earthing Connection of Main Tank, Neutral Bushing, Marshalling Box, Control Gear Box, Cable Box, Arcing-Horn, etc., are correctly made.

Rajasthan Powergen

Bushing arcing horn gap is set correctly

Rajasthan Powergen

All CT Secondary Circuits are Closed

Rajasthan Powergen

All Air-Release Plugs of Main Tank, Radiator, Conservator, Buchholz Relay, Bushings, etc., are free of air pocket/bubbles

Note: After Oil-Filling or Before Commissioning, AT LEAST 12hrs should be allowed for the oil to settle-down and the air is released from all points at 2 hourly intervals

5.3.2
It is recommended that the transformer is initially energized at NO-LOAD only and checked for any abnormalities for the next 6 to 8 hours

5.3.3
AFTER SWITCHING on no-load, if the Primary side Circuit Breaker is tripped, investigate the cause thoroughly and re-energize the transformer ONLY AFTER ensuring that the fault is properly cleared

5.3.4
If satisfactory (transformer on No-Load) then apply load gradually and observe for any abnormalities for the next 6 to 8 hours

5.3.5
If the transformer is satisfactory on-load up to 50% for the first 4-8 hours, shut-down the transformer and ensure that all air-release plugs of the tank, radiator, conservator, Buchholz relay, bushing, etc., are free of air pockets which might have developed during initial loading