Transformer Commissioning Procedure |
||
5.0 COMMISSIONING |
||
5.1 PURPOSE | ||
5.1.1 After the satisfactory completion of installation, the following pre-commissioning checks, and tests on instruments must be performed before putting the transformer into service. Prior to commissioning work, for specific help and information on the accessories supplied, refer to the manufacturer’s instruction booklet/product catalog, etc., furnished with the handing-over documents |
||
5.2 COMMISSIONING TESTS |
||
5.2.1 Insulation Resistance (IR) |
||
Before starting this test all the power terminal bushings should be thoroughly cleaned with a dry clean piece of cloth. |
||
At all the tap positions, IR values of windings to earth & between windings shall be measured with designated insulation tester of suitable ratings and readings noted. Between HV Winding and Earth (Megger) use 5000V or 2500V Insulation Tester |
||
IR values obtained should be similar to those indicated in the manufacturers’ test report, furnished with the handing –over documents. In humid weather, IR values obtained may be lower due to condensation on the terminal bushings |
||
If IR values are very low and unacceptable, then it may be necessary to filter the oil / dry-out the winding till the insulation reaches satisfactory values. |
||
5.2.2 Break-Down Voltage (BDV) Test: |
||
Oil samples from tank bottom, tank top, radiator, etc. shall be carefully taken and tested for BDV value, as per clause 4.3 of this manual. |
||
BDV value of oil should be more than 50kV (rms) for 1 minute in the standard test cell |
||
If BDV value is very low and unacceptable (30kV(rms) or less for 1 minute, then it may be necessary to dry-out & clean the oil till the insulation reaches satisfactory values. |
||
Note: For very low IR values and low BDV values, it is recommended to contact suppliers or manufacturer for suitable recovery procedure based on available facilities at site |
||
5.2.3 Voltage Ratio Test |
||
Apply 3-Phase, 433V AC supply on the HV side and the Voltage Ratio at all tap positions can be derived using suitable precision voltmeter connected to the LV side. A ratio meter, if available can be used for a more accurate measurement |
||
The Ratio value obtained should be similar to those indicated in the manufacturers’ test report, furnished with the handing-over documents. |
||
5.2.4 Winding Resistance Measurement Test |
||
Winding Resistance of every phase of each winding should be measured using a suitable DC Resistive Bridge or similar. |
||
Winding Resistance values obtained should be similar to those indicated in the manufacturers’ test report, furnished with handing-over documents |
||
5.2.5 Marshalling Box Scheme Check |
||
All the auxiliary wiring from various accessories to marshaling box shall be checked with marshaling box scheme drawing furnished with the handing-over documents. |
||
During testing of accessories like Buchholz relay, etc., an operation of all the alarm/trip contacts shall be checked at marshaling box terminal blocks ensuring both operation and wiring are checked correctly |
||
5.2.6 Buchholz Relay Test |
||
Relay operation for alarm and trip contact shall be checked by injecting air inside the relay through test petcock. Injected air collected inside the relay allows the alarm float/flap & trip float/flap to fall thereby operating their respective switch |
||
5.2.7 Temperature Indicator Test |
||
Indicators operation for alarm and trip contact shall be checked by manual stimulation |
||
5.2.8 Off-Circuit Tap Selector (OCTS) |
||
During shipment, the OCTS has not been separated from the transformer so it is not necessary to recheck the internal connections of tapping an internal mechanism |
||
Means of protecting the OCTS from unauthorized operation is provided by using a padlocking arrangement at the designated tap position |
||
5.3 SENSIBLE ADDITIONAL CHECKS |
||
5.3.1 BEFORE SWITCH ON ENSURE that |
||
All the Oil Shut-off Valves are OPEN and Draw-Off Valves are CLOSED |
||
All Thermometer Pockets are near filled (85%) with oil. |
||
Oil is at the correct level in the Bushings, Conservator, etc |
||
Desiccant color in breather is blue for silica-gel or yellow/orange for envirogel |
||
Earthing Connection of Main Tank, Neutral Bushing, Marshalling Box, Control Gear Box, Cable Box, Arcing-Horn, etc., are correctly made. |
||
Bushing arcing horn gap is set correctly |
||
All CT Secondary Circuits are Closed |
||
All Air-Release Plugs of Main Tank, Radiator, Conservator, Buchholz Relay, Bushings, etc., are free of air pocket/bubbles |
||
Note: After Oil-Filling or Before Commissioning, AT LEAST 12hrs should be allowed for the oil to settle-down and the air is released from all points at 2 hourly intervals |
||